Water Woes 

Construction of CBU storm-water detention basin contaminates Lick Creek.

click to enlarge A recent photo of a muddy Lick Creek, near the V&E Greenline. - NAOMI VAN TOL
  • naomi van tol
  • A recent photo of a muddy Lick Creek, near the V&E Greenline.

When city officials sought to reassure Midtowners that they wouldn't notice a proposed 18-foot storm-water detention basin in Overton Park, they cited a similar project at Christian Brothers University.

But that detention basin, currently under construction, has already caught the eye — and nose — of local residents.

Usually, Lick Creek in Vollintine-Evergreen is crystal clear.

"Even though it's an urban creek, it's very clear water," says neighborhood resident Mary Wilder. "Probably about the first of June, there would be episodic periods of brown water. Sometimes it was so brown you couldn't see the bottom of the creek and, normally, you can."

At the same time, Naomi Van Tol with the Citizens to Preserve Overton Park noticed that the water in the park's section of Lick Creek smelled distinctly like sewage.

Van Tol and Wilder, both members of the Lick Creek Storm Water Coalition, called the city's storm-water division and reported the problem.

"The last few rains were so heavy that it just became constant, and, at that point, we figured it out real quick," Wilder says. "I went over to Overton Park where there's a confluence of three bayous and creeks. You can see the three inlets as they join together. One was clear, another was clear, and one was full of mud."

The ironical culprit: city construction to create a storm-water detention basin on CBU's soccer fields.

Because the project at CBU includes more than an acre of land, the city's engineering department was required to get a general construction storm-water discharge permit from the state department of environment and conservation (TDEC). The state then lends its authority to the city to do inspection and enforcement.

"They had discharge of silt and soil from the large rain event around July 17th," says Scott Morgan, manager of the city's storm-water department. "They had erosion control problems in place before the storm event. The rain essentially blew out their erosion control measures."

The city issued a Notice of Violation, or NOV, to the city engineers, and Morgan says corrective action already has been taken.

"They have a due date with the NOV. If corrective actions have not been taken by the due date, we'll do a follow-up inspection and fines or environmental citations can be issued," Morgan says.

TDEC's Division of Water Pollution Control is currently completing their inspection report and considering an additional NOV or enforcement actions.

Comments (6)

Showing 1-6 of 6

Add a comment

 
Subscribe to this thread:
Showing 1-6 of 6

Add a comment

ADVERTISEMENT
ADVERTISEMENT

Blogs

News Blog

MATA Security Guard Placed on Diversion in Passenger Death

News Blog

Top Guns: Shelby Tops Tennessee in Handgun Permits

Film/TV/Etc. Blog

Movies and Video Games Meet at the Cossitt Library

News Blog

President Jimmy Carter Discusses His Work with Habitat

Politics Beat Blog

Haslam, in Memphis, Suggests Calling Special Session

Film/TV/Etc. Blog

Politics and the Movies 3: Olympia

Intermission Impossible

"Small and Essential," New Quark Theatre Company Offers Alternatives

Intermission Impossible

Disgraced Sets A Course for Conflict

ADVERTISEMENT

More by Mary Cashiola

Readers also liked…

ADVERTISEMENT
© 1996-2016

Contemporary Media
460 Tennessee Street, 2nd Floor | Memphis, TN 38103
Visit our other sites: Memphis Magazine | Memphis Parent | Inside Memphis Business
Powered by Foundation